Tesla won a bid in July to build the 129 megawatt hour battery for South Australia, the country’s most wind power-dependent state, with a vow from chief executive Elon Musk to install it within 100 days of signing a grid connection agreement or give it to the state for free.
When the grid connection deal was signed on 29 September, Tesla was already half way through installing the battery packs.
The Tesla Powerpacks have now been fully installed at a wind farm run by France’s Neoen, and testing is set to begin to provide grid security services in South Australia.
“While others are just talking, we are delivering our energy plan, making South Australia more self-sufficient, and providing back up power and more affordable energy for South Australians this summer,” state Premier Jay Weatherill said in a statement.
The state has yet to say how much it would pay for the battery, which is part of a A$510m (£291.38m) plan that includes diesel-fired generators to help keep the lights on following a string of blackouts over the past 18 months.
Australia’s energy market operator has warned that power supply will be tight this summer, particularly in South Australia and neighbouring Victoria, where one of the market’s biggest coal-fired power plants was shut in March.
Tesla completes construction of the world’s largest lithium ion battery
Tesla has completed construction of the world’s largest lithium ion battery in Australia, putting it on track to meet a 100-day deadline for switching the battery packs on, the South Australian government said on Thursday.Tesla won a bid in July to build the 129 megawatt hour battery for South Australia, the country’s most wind power-dependent state, with a vow from chief executive Elon Musk to install it within 100 days of signing a grid connection agreement or give it to the state for free.
When the grid connection deal was signed on 29 September, Tesla was already half way through installing the battery packs.
The Tesla Powerpacks have now been fully installed at a wind farm run by France’s Neoen, and testing is set to begin to provide grid security services in South Australia.
“While others are just talking, we are delivering our energy plan, making South Australia more self-sufficient, and providing back up power and more affordable energy for South Australians this summer,” state Premier Jay Weatherill said in a statement.
The state has yet to say how much it would pay for the battery, which is part of a A$510m (£291.38m) plan that includes diesel-fired generators to help keep the lights on following a string of blackouts over the past 18 months.
Australia’s energy market operator has warned that power supply will be tight this summer, particularly in South Australia and neighbouring Victoria, where one of the market’s biggest coal-fired power plants was shut in March.
Views: 335
©ictnews.az. All rights reserved.Similar news
- Azerbaijani project to monitor disease via mobile phones
- Innovative educational system to be improved under presidential decree
- NTRC prolongs license of two TV and radio organizations for 6 years
- Azerbaijan establishes e-registry for medicines
- Azerbaijani museum introduces e-guide
- Nar Mobile opens “Nar Dunyasi” sales and service center in Siyazan city
- International conference on custom electronic services held in Baku
- OIC secretary general to attend COMSTECH meeting in Baku
- Azerbaijan develops earthquake warning system
- New law to regulate transition to digital broadcasting in Azerbaijan
- Azerbaijani State Social Protection Fund introduces electronic digital signature
- Intellectual traffic management system in Baku to be commissioned in December
- Tax Ministry of Azerbaijan started receiving video-addresses
- World Bank recommends Azerbaijan to speed up e-service introduction in real estate
- Azerbaijan to shift to electronic registration of real estate